Bridges
Monthly Update #3
8
June 2005
BRIDGE 1506 IN
Bridge
improvements on both properties are still being advanced. Last year’s accomplishments were
considerable, and this year’s are also above average. The overall goal is to continue to strengthen
bridges to allow for 286,000 loading from
Of
the 10 major bridges scheduled to be repaired this year, we have completed none
of them, but all of them are currently works-in-progress. All bridgework is scheduled to be completed
by October 31, 2005. It is very early in
the construction season, but it appears we will meet that schedule. By far, the largest and most complicated
bridge project is the Fort Pierre, South Dakota bridge,
#1506, on the DM&E’s PRC sub, which is being
completely rebuilt to 315,000 pound standards.
·
The 1506 bridge in
·
Bridge 464.5 at Sleepy Eye was completed late last week
·
Jamie Stark’s New Ulm crew has been working
on several bridges in the Revere CWR territory to complete their upgrade.
·
Jay Harris’ and Ken Luensman’s crews have
just completed redecking a large section of the
Truman drawbridge in
·
The crews from