Bridges
Monthly Update #4
13
July 2005
BRIDGE 1506 IN
Bridge
improvements on both properties are still being advanced. Last year’s accomplishments were
considerable, and this year’s are also above average. The overall goal is to continue to strengthen
bridges to allow for 286,000 loading from
Of
the 10 major bridges scheduled to be repaired this year, we have completed one
of them and one other will be completed very soon. All of the remaining bridges are currently
works-in-progress. All bridgework is
scheduled to be completed by October 31, 2005.
It appears we will meet that schedule.
By far, the largest and most complicated bridge project is the Fort
Pierre, South Dakota bridge, #1506, on the DM&E’s PRC sub, which is being completely rebuilt to
315,000 pound standards.
·
The 1506 bridge in
·
Bridge 464.5 at Sleepy Eye was completed late last month
·
Jamie Stark’s New Ulm crew has been working
on several bridges in the Revere CWR territory to complete their upgrade.
·
Jay Harris’ and Ken Luensman’s crews have
just completed redecking a large section of the
Truman drawbridge in
·
The crews from