Rail
Monthly Update #2
11
May 2005
CWR PROGRAM OVER 50% COMPLETED!!!
To date, we have installed over 21 of the roughly 38
track miles scheduled to be completed by the end of the production season. The 30 miles scheduled to be laid by RJ Corman will be completed by the end of May. This Corman crew was
the same crew that laid over 60 track miles on the DM&E in 2004 and nearly
90 miles of CWR on the
¨ RJ Corman
completed the first 15 miles of CWR between
¨ This Corman
crew has just today, the 11th of May, finished 50% of the
¨
¨ Darren LeGarre’s
switch and crossing crew has already assembled and installed 6 switches at
¨ Randy Parmenter’s
switch and crossing crew has been assembling switches and will begin installing
these switches shortly for the