Rail
Monthly Update #3
8
June 2005
CWR PROGRAM OVER 75% COMPLETED!!!
To date, we have installed over 32 of the roughly 40
track miles scheduled to be completed by the end of the production season. The 30 miles scheduled to be laid by RJ Corman was completed before the end of May. This Corman crew
was the same crew that laid over 60 track miles on the DM&E in 2004 and
nearly 90 miles of CWR on the
¨ RJ Corman
completed the first 15 miles of CWR between
¨ This same Corman crew completed the second 15 mile section of CWR
north of
¨
¨ Jack Boxleiter
is supervising the tie installation, curve rail replacement, surfacing and
clean up efforts on the double track, and will continue to assist Mr. Goffinet
with this year’s capital projects on the IC&E.
¨ Steve Koser’s
crew has installed curve rail on 4 curves on the double track to complete his
crew’s work in that area this year.
¨ The LA Colo
crew has installed new rail in several curves on the east end of the
¨ Darren LeGarre’s
switch and crossing crew has already assembled and installed 6 switches at
¨ Randy Parmenter’s
switch and crossing crew has been assembling switches and installing them this
week on the