Rail
Monthly Update #6
14
September 2005
CWR PROGRAM OVER 90% COMPLETED!!!
To date, we have installed over 36 of the roughly 40
track miles scheduled to be completed by the end of the production season. The 30 miles scheduled to be laid by RJ
Corman was completed before the end of May.
This Corman crew was the same crew that laid over 60 track miles on the
DM&E in 2004 and nearly 90 miles of CWR on the
¨ RJ Corman completed the
first 15 miles of CWR between
¨ This same Corman crew
completed the second 15 mile section of CWR north of
¨
¨
¨
¨ The LA Colo crew has
installed new rail in several curves on the east end of the
¨ Darren LeGarre’s
switch and crossing crew has completed the installation of the switches on the
CWR project and will finish the year on the Hanska
project in New Ulm as well as assisting with a switch
project near Colony
¨ Randy Parmenter’s
switch and crossing crew has installed all of the switches on the CWR project
area and will finish their year on crossings and joint ties.