Rail
Monthly Update #7
19
October 2005
10 MILES OF CWR ADDED TO 2005 CWR PROJECTS!!!
To date there has been 38 miles of CWR installed on the
two properties out of the 50 miles that is now scheduled. The last project is a 10 mile project on track
#2 of the
¨
¨
¨ Jack will also oversee the
installation of the new 10 mile CWR project between Mosby
Jct and
¨ Darren LeGarre’s
switch and crossing crew has completed the installation of all the switches on
the DM&E. They will complete the
year with a couple more crossings on the
¨ Randy Parmenter’s
switch and crossing crew has completed the installation of all of the switches
on the IC&E and will complete the year installing joint ties on the west
end of the Mason City sub.