Rail
Weekly Update #1
13
April 2005
OFF AND RUNNING ON CWR PROGRAM
To date, we have installed nearly 5 of the roughly 38
track miles scheduled to be completed by the end of the production season. The 30 miles scheduled to be laid by RJ Corman will be completed by the end of May. The RJ Corman crews
have been on both properties for the last few weeks distributing material and
getting equipment in place in anticipation of this years’
projects. This Corman
crew was the same crew that laid over 60 track miles on the DM&E in 2004
and nearly 90 miles of CWR on the
¨ RJ Corman
started, as scheduled, at
¨ Two rail trains were
delivered to each property during the first quarter and all unloading went
without incident. The last rail train
scheduled for this year’s program, the “Curve Patch” project train, will be
welded the last week of April with delivery and unloading scheduled before the
middle of May.
¨
¨ Darren LeGare’s
switch and crossing crew has already assembled two switches at