System-Wide
Monthly Update #3
8,
June 2005
The 2005 production season has been proceeding well for the last two months and the engineering forces have been very busy scheduling the distribution of ties and other materials that were in the original capital program as well as the seven additional projects that were added last month. The CWR projects for 2005 are already over 75% completed and the tie and surfacing projects are over 33% and 25% completed respectively.
¨ All 5 rail trains (nearly
400,000 feet) have been delivered and unloaded by the second week of May. The two major projects of 15 track miles each,
one near
¨ The “Curve Patch” program
for 2005 will include laying over 75,000 feet of premium rail on over 35 curves
between Nora Junction on the Mason City sub, to Airline Junction on the Kansas
City sub. Work was started on this curve
project last week.
¨ Due to the additional
Capital projects that have recently been added to the 2005 capital program, major
tie projects are scheduled to be completed on the Kansas City, River, Chicago,
and Owatonna subs of the IC&E and the Tracy and PRC subs of the
DM&E. There will be lesser projects
on the
¨ The most notable bridge
projects of 2005 are the complete rebuild of Bridge 1506 at
¨ All materials for all
projects seem to be in good supply and will be readily available, although high
steel and fuel prices have hampered some deliveries and have raised the prices
on many items.
¨ There are now 30 new premium
turnouts in the 2005 capital plan with 15 of them being associated with the CWR
projects and the rest for various upgrades around the two properties.
¨ Current estimates are for
about 220,000 tons of ballast for the 2005 season’s 750 miles of surfacing.