System-Wide
Monthly Update #4
13,
July 2005
The 2005 production season has been proceeding on or ahead of schedule in all areas since start up several months ago. Tie and surfacing programs are nearing 50% completion and bridge projects are over 60% complete for the year. This season’s CWR programs are approaching 90% completion and will be 100% completed by the end of the 3rd quarter this year.
¨ All 5 rail trains (nearly
400,000 feet) were delivered and unloaded earlier this year and nearly 90% of
the 2005 CWR program has been completed. The two major CWR programs this year near
¨ The “Curve Patch” program
for 2005 includes laying over 75,000 feet of premium rail on over 35 curves
between Nora Junction on the Mason City sub, to Airline Junction on the Kansas
City sub. Work on this program was
started last month and all curves on the
¨ We are now scheduled to
install approximately 185,000 ties in the 2005 season across the two systems. We now expect all of these projects to be
completed by the end of October.
¨ The most notable bridge
projects of 2005 are the complete rebuild of Bridge 1506 at
¨ Most materials for all
projects seem to be in good supply and will be readily available, although high
steel and fuel prices have hampered some deliveries and have raised the prices
on many items.
¨ There are now 30 new premium
turnouts in the 2005 capital plan with 15 of them being associated with the CWR
projects and the rest for various upgrades around the two properties. Over 50% of the turnouts are already installed
and the rest are scheduled to be installed by the end of September
¨ Current estimates are for
about 220,000 tons of ballast for the 2005 season’s 750 miles of surfacing.