System-Wide
Monthly Update # 6
14,
September 2005
The 2005 production season has been proceeding well for the past several months. The engineering forces have essentially completed most of the CWR projects and all of the tie distribution that was scheduled for the 2005 production season. Bridge work, tie installation, surfacing and several switches will be installed yet this year and we fully expect all projects to be completed, on time and on budget by the end of the year.
¨ Both large CWR projects, one
north of
¨ The “Curve Patch” program
for 2005 will include laying over 75,000 feet of premium rail on over 35 curves
between Nora Junction on the Mason City sub, to Airline Junction on the Kansas
City sub. Work on this program is over
90% completed and will be 100% completed within the next four to six weeks.
¨ Due to the additional
Capital projects that have recently been added to the 2005 capital program,
major tie projects are scheduled to be completed on the
¨ The most notable bridge
projects of 2005 are the complete rebuild of Bridge 1506 at
¨ All materials for all
projects have been in good supply and have been readily available, although
high steel and fuel prices have hampered some deliveries and have raised the
prices on many items. Most materials
have been delivered and are on site ready for installation.
¨ There are now 30 new premium
turnouts in the 2005 capital plan with 15 of them being associated with the CWR
projects and the rest for various upgrades around the two properties. All turnouts are scheduled to be installed by the
middle of October.
¨ Current estimates are for
about 220,000 tons of ballast for the 2005 season’s 925 miles of surfacing.