System-Wide
Monthly Update # 7
19,
October 2005
The 2005 production continues to progress well, and even
though there have been some project delays, we still expect all projects to be
completed by the end of the production season. We have had an additional
project approved by the board just recently and that is a 10 mile CWR project
on track # 2 through
¨ Both large CWR projects, one
north of
¨ The “Curve Patch” program
for 2005 will include laying over 75,000 feet of premium rail on over 35 curves
between Nora Junction on the Mason City sub, to Airline Junction on the Kansas
City sub. There are only 3 curves left on
this project all on the River sub which will be done by Mr
Koser’s crew after the
¨ The last two tie projects to
be completed will be the 20,000 ties on the River sub of the IC&E which is
just getting started and the 10,000 ties on the PRC of the DM&E which is
about ½ completed.
¨ The
¨ The most notable bridge
projects of 2005 are the complete rebuild of Bridge 1506 at
¨ All materials for all
projects have been in good supply and have been readily available, although
high steel and fuel prices have hampered some deliveries and have raised the
prices on many items. All materials have
been delivered and are on site ready for installation.
¨ Thirty new premium turnouts
have been delivered and installed on the two properties.
¨ Current estimates are for
about 220,000 tons of ballast for the 2005 season’s 925 miles of surfacing.