Ties
Monthly Update #2
11
May 2005
THREE TIE PROJECTS DONE!!
The
additional capital that was just recently approved has added 100,000 ties to
our Capital program meaning we now have nearly 185,000 ties to install in the
2005 production season. These ties are
still scheduled to be installed with 3 railroad crews and one contractor by the
end of October.
¨ The DM&E West tie gang,
under foreman Jim Nemec, has already installed ties
on the Crawford sub and the east end of the PRC. They are now working on the west end of the
PRC. This crew has a total of 26,000
ties to install in this production season, mostly on the PRC.
¨ The DM&E east tie gang (foreman
Kim Camp) has already completed two small projects. The first project was 2,500 ties on the
Hartland sub and the second project was the Waseca sub for another 2,500 ties.
This crew’s last scheduled project for the year is 26,000 ties on the
¨ Steve Koser’s
IC&E tie crew started this year on the double track of
¨ Contractor LA Colo started his production this year on the
¨ As of May 11, 2005, nearly
90,000 ties have been delivered and unloaded on the two properties.
¨ The remaining 95,000 ties
that are now required to be delivered because of the added capital projects are
expected to be on the property by the end of June.
¨ As of May 11th,
over 45,000 ties have already been installed.