Ties
Monthly Update #3
8
June 2005
SIX TIE PROJECTS DONE!!
The
tie crews on both properties have already installed over 65,000 ties. This is over 35% of the 185,000 ties now
allocated for the 2005 production season. These ties are still scheduled to be installed
with 3 railroad crews and one contractor by the end of October.
¨ The DM&E West tie gang, (foreman
Jim Nemec), has already installed ties on the
Crawford sub and the east end of the PRC.
They are completing a project this week on the extreme west end of the
PRC. This crew has a total of 26,000
ties to install in this production season, mostly on the PRC.
¨ The DM&E east tie gang
(foreman Kim Camp) has already completed two small projects. The first project was 2,500 ties on the
Hartland sub and the second project was the Waseca sub for another 2,500 ties.
This crew’s last scheduled project for the year is 26,000 ties on the
¨ Steve Koser’s
IC&E tie crew started this year on the double track at
¨ Contractor LA Colo started his production this year on the
¨ Since the
¨ LA Colo
has also completed the installation of 7,500 ties on the
¨ As of June 8th
2005, nearly 145,000 ties have been delivered and unloaded on the two
properties.
¨ The remaining 40,000 ties
that are now required to be delivered because of the added capital projects are
expected to be on the property by the end of June.
¨ As of June 8th,
over 65,000 ties have already been installed.