Ties
Monthly Update #4
13
July 2005
TIE PROJECTS CONTINUE ON SCHEDULE!!
The
tie crews on both properties have already installed over 90,000 ties. This is nearly 50% of the 185,000 ties now
allocated for the 2005 production season. These ties are still scheduled to be installed
with 3 railroad crews and one contractor by the end of October.
¨ The DM&E West tie gang, (foreman
Jim Nemec), has so far this year completed tie
projects on the Crawford, lower Black Hills and the west end of the PRC. They will complete a project near
¨ The DM&E east tie gang
(foreman Kim Camp) continues to improve on their production as they progress
through their third project of the year near New Ulm.
Already completed are projects on the
Hartland and Waseca subs and this crew will complete their nearly 35,000 tie
year on the
¨ Steve Koser’s
IC&E tie crew started this year on the double track at
¨ Contractor LA Colo has
installed 10,000 ties on the
¨ As of June 11th
2005, nearly 165,000 ties have been delivered and unloaded on the two properties.
¨ The remaining 20,000 ties
that are now required to be delivered because of the added capital projects are
now expected to be on the property by the end of July.
¨ As of July 13th,
over 90,000 ties have already been installed.