SEVERAL TIE PROJECTS COMPLETED, FOUR
REMAINING!!
The
tie crews on both properties have already installed nearly 140,000 ties. This is over 75% of the 185,000 ties now
allocated for the 2005 production season. The remainder of these ties
are still scheduled to be installed with our three railroad crews by the
end of October or early in November.
¨ The DM&E West tie gang, (foreman
Jim Nemec), has already installed ties on the
Crawford sub, the east end of the PRC, west end of the PRC and the upper Black
Hills subs this year. They will now
spend the rest of the year on projects on the PRC near Wall and Van Meter on
the PRC sub.
¨ The DM&E east tie gang
(foreman Kim Camp) has already completed two small projects on the Hartland and
Waseca subs and has been working on a major project on the
¨
¨ Contractor LA Colo started
his production this year on the
¨ LA Colo has also installed
10,000 ties on the
¨ As of September 13th
2005, all 185,000 ties have been delivered and unloaded on the two properties.
¨ As of September 13h,
over 140,000 ties have already been installed.