Bridges
Monthly Update #12
15
December, 2007
ANOTHER BIG YEAR FOR BRIDGE CREWS ON BOTH
RAILROADS!
The two properties had
nearly $5 million in bridge work scheduled for the 2007 season. Much of this work was scheduled in conjunction
with the “west end” project, but a significant amount of major repairs were
made across both properties. A summary
of the major projects is listed below.
·
Bridge 1845 at MP 610 on the DM&E’s PRC
Subdivision has received a complete rebuild and was completed in the 2nd
quarter. E- 80 crews with Monty Unseth and Mel Hershberger were the foreman for the two
crews that completed the work on this project. Monty is the crew that specializes in the wood
parts of the bridge and Mel’s crew specializes in steel structures, including
the pile driving.
·
Mel’s E-80 crew went to the bridge # H308 on
the
·
Mel’s crew then worked on bridge H313 in
Belle Fourche over the
·
Bridge H-367 near Colony,
·
Bridge R-64 near MP 9 on the IC&E’s Mason
City Subdivision was scheduled to start replacement in late 2007.
·
Local track and bridge crews completed the
re-decking and rail replacement on the
·
Late floods in eastern