Rail
Monthly Update #4
25,
April 2007
SEVEN MAJOR RAIL PROJECTS SCHEDULED FOR 2007
PRODUCTION SEASON!! NEARLY ONE HUNDRED &
SEVENTEEN MILES OF CWR TO BE INSTALLED ON THE TWO PROPERTIES DURING THE
CONSTRUCTION SEASON.
¨ A thirty mile project of new
115# CWR is scheduled to start between Colony, WY and Sturgis, SD on
Wednesday, April 25th. This
project will eliminate all jointed rail on the Upper Black Hills sub north of Rapid City. Rick Hanson will be the EIC (
Employee in Charge) for this project with Jim Nemec
as Project Supervisor.
¨ A twenty-two mile project
between Rapid City
and Owanka and the installation of 10 turnouts was
started this Monday, April 23rd by the LA Colo
contracting group. Bill Bussell is the EIC for this project, again with Jim Nemec as Project Supervisor. Another part of this project is the extension
of Wall siding so that trains can meet more efficiently.
¨ A seven and one half mile
136# CWR project in the Pierre/Fort Pierre area will include the installation
of rail as well as 7 new turnouts in the area. This rail project will also be done by the LA Colo group assisted by DM&E personnel for the switch
and crossing installations.
¨ We are also scheduled to
install 22 miles of rail between Sleepy Eye, MN and Mankato, MN
in 2007. Along with the rail there will
be 12 new turnouts installed in this corridor. The RJ Corman group
has been selected to install this rail with the projected starting date near
the end of June.
¨ On the west end of the IC&E’s Mason City sub we
will have a CWR project of seven and one/half miles just west of Algona, IA.
This new 115# CWR will also include the
installation of 4 new turnouts and is scheduled for a June or July installation
by a contractor who has not yet been selected.
¨ A Marquette
sub project north of Dubuque,
IA will include the installation
of about 8 miles of new 136# rail and is scheduled for early May. This project will eliminate the jointed rail
between Dubuque and Marquette. The RJ Corman group
has been selected to install this rail with the project scheduled to start in
mid-June.
¨ Another Marquette
sub project of 15 miles of new 136# CWR will eliminate the jointed rail between
Dubuque and Samoa, IA. This project also includes installation of new
power assisted switches at Green
Island to increase
efficiency in this location. The RJ Corman group has been selected to install this rail with
the project beginning on May 2nd and being completed in early June.
¨ The total number of turnouts
that will be installed with the CWR programs as well as other projects is now
scheduled to be sixty-seven for the 2007 season.