Ties
Monthly Update #12
15
December 2007
NEARLY 200,000 TIES INSTALLED IN 2007!! TWELVE MAJOR PROJECTS HIGHLITE THE PRODUCTION YEAR.
The
two Company tie crews and three contractor crews enabled the two properties to
install over 200,000 ties in 2007. More
details of all tie projects scheduled for 2007 are below:
¨ The first project on the two
properties to be completed was one of nearly 12,000 ties on the IC&E’s
¨ The second project on the
two properties to be completed was one of 14,000 ties on the Upper Black Hills
Subdivision and in the
¨ The third project that was
completed on the two properties was one of 20,000 ties on the Marquette
Subdivision between
¨ The next project on the two
properties that was completed is one of 22,000 ties on the upper end of the
Marquette Subdivision, between
¨ From the Black Hills
Subdivision the West DM&E tie gang traveled to
¨ On the IC&E, the
DM&E tie gang installed nearly 40,000 ties on the West Mason City sub, the
¨ The Railworks tie crew
installed nearly 11,000 ties on the south end of the
¨ John Thulen’s
IC&E crew completed two projects by installing 2,500 ties in the Nahant
yard and 12,000 ties in the main line west of Nahant. These projects were completed in late July.
¨ After the Nahant projects
were completed, the IC&E crew proceeded to install CWR in several curves on
the River sub. When this is completed,
the crew will complete their 2007 tie installation schedule by installing
22,000 ties between Chillicothe, Missouri and Polo, Missouri. The IC&E tie crew is scheduled to complete
all of their tie installation by mid-September and then will install curve rail
for the remainder of the 2007 production year.
¨ The H&H tie crew
installed nearly 12,000 ties between
¨ The LA Colo tie crew
installed nearly 8,000 ties on the east end of the