FIVE MAJOR RAIL PROJECTS SCHEDULED FOR THE 2008
PRODUCTION SEASON!! OVER 50 MILES OF CWR
TO BE INSTALLED THIS YEAR!!
Five major projects will headline the 2008 production year.
¨ The first project to be
started in 2008 will be one of nearly 20 miles between
¨ A small project of nearly
five miles will be the next one completed in the Iroquois, SD area of the Huron
sub
¨ The third project area is
one of seven miles between
¨ The fourth and last project
for the DM&E’s portion of the 2008 CWR schedule is one of nearly 8 miles
west of
¨ The final major CWR project
of the year is on the IC&E and will involve nearly 15 miles of used CWR for
the west end of the Mason City sub between Hobarton
and Emmetsburg.
¨ The last of the actual CWR
projects is the annual curve project which this year will involve nearly 9
miles of premium rail for curve replacement on the KC, River,
¨ Over 40 turnouts will be
installed in conjunction with these CWR projects as well as other project
needs. Turnouts will be supplied by
Progress Rail and Nortrak.
¨ All CWR will be supplied by
LB Foster and Progress Rail Services.
¨ CWR will be installed by the
RJ Corman group starting in mid May with a scheduled completion in August.