Ties
Monthly Update
26,
March 2007
NEARLY 230,000 TIES TO BE
INSTALLED IN 2008 CAPITAL PROJECTS. ELEVEN
MAJOR PROJECTS PLUS SEVERAL MINOR ONES WILL HIGHLITE THE PRODUCTION YEAR!
Tie
crews on the two properties will again have another banner year installing
nearly 230,000 main line and yard track ties. More details of all tie projects scheduled for
2008 are below:
¨ The IC&E tie gang will
start its production season on March 31st in
1.
KC sub, 12,000 ties on track #1 between Airline Jct
and Moseby J ct.
2.
KC sub, 22,000 ties on single track between Polo and
3.
There are 2500 yard ties for yard tracks in
4.
On the river, there are over 10,000 ties scheduled to be installed in
two locations, the first is near the waterworks area and the second area is
between the UP/IC&E 5th street plant at
5.
6.
The remainder of the IC&E crew’s year will be occupied with curve
rail replacement.
¨ The DM&E tie crew will
start its production season on April 14th and is now prepared to
follow the schedule listed below:
1.
West Mason City sub, 45,000 ties, between Hartley and
2.
1,000 ties for
3.
7,000 ties on
4.
5.
1,000 ties for the
6.
7.
Waseca sub 10,000 ties between
8.
2,000 ties for the Waseca yard.
9.
6,000 ties between Waseca and
10. 2,000 Huron yard ties.
11. 5,000 ties on the lower
¨ We are currently scheduling
the following work for the LA Colo contracting tie crew which is now scheduled
to start tie installation on April 7th and follow the schedule
listed below:
1.
2.
1,000 ties in
3.
4.
5.