Bridges
Weekly Update #2
22
April 2004
ON SCHEDULE
Of
the 146 bridges scheduled to be repaired this year, we are completed with 10 of
them, and 6 of them are currently works-in-progress. All bridge work is scheduled to be completed by November 1,
2004. As of now, it appears we will
meet that schedule. Piling continues to
be driven at the Sioux River Bridge. So
far everything is on schedule.
¨
E-80
and Osmose are both working between Brookings and Manchester on RRIF bridges.
¨
The
Sioux River Bridge is being worked on by E-80.
Prep work began on March 15th. April 12th they started driving piling, 12 of 78
pilings have been driven thus far. The
track and approach has been raised 16”.
It is on schedule and will be completed by November 1, 2004.
¨
The
Cottonwood and Mine Creek bridges are slated to begin May 15, 2004 and
completed July 15, 2004.