Bridges
Weekly Update #4
6
May 2004
ON SCHEDULE
Of
the 146 bridges scheduled to be repaired this year, we are completed with 18 of
them, and 8 more are currently works-in-progress as of May 6th. All bridge work is scheduled to be completed
by November 1, 2004. As of now, it
appears we will meet that schedule.
Piling continues to be driven at the Sioux River Bridge. So far everything is on schedule.
¨
E-80
and Osmose are both working between Elkton and Wolsey on RRIF bridges.
¨
The
Sioux River Bridge is being worked on by E-80.
Prep work began on March 15th and on April 12th they started driving
piling with 30 of 78 pilings being
driven thus far. The track and approach
has been raised 16”. It is on schedule
and will be completed by November 1, 2004.
¨ The Cottonwood and Mine Creek bridges are slated to begin May 15, 2004 and completed July 15, 2004.
¨ Gage Brothers in Sioux Falls is building the ballast tubs for the Mine Creek and the Sioux Valley Bridges.