Bridges
Weekly Update #7
27
May 2004
ON SCHEDULE
Of
the 146 bridges scheduled to be repaired this year, we are completed with 33 of
them, and 8 more are currently works-in-progress as of May 27th. All bridge work is scheduled to be completed
by November 1, 2004. As of now, it
appears we will meet that schedule.
Pile driving has been completed on the east end of the Sioux River
Bridge. So far everything is on
schedule.
¨
E-80
and Osmose are both working between Elkton and Wolsey on RRIF bridges.
¨ The Sioux River Bridge is being worked on by E-80. Prep work began on March 15th and on April 12th they started driving piling with 36 of 78 pilings being driven thus far. This completes the pile driving that is required for the east end of the bridge. For the next two months the crew will be working on the concrete caps and abutments, which will be poured in place. The first of these concrete caps was poured on Wednesday the 26th. The crew will complete the east end of the bridge before they travel to the west side to start the other half of this project. This project is on schedule and should be completed by November 1, 2004.
¨ The Cottonwood and Mine Creek bridges are now slated to begin June15, 2004 and completed August 15, 2004.