Bridges
Weekly Update #12
30
June 2004
ON SCHEDULE
Of
the 146 bridges scheduled to be repaired this year, we are completed with 44 of
them, and 9 more are currently works-in-progress as of June 30th.
All bridgework is proceeding on schedule to be completed by November 1,
2004. Span changeout has begun on the
east end of the Sioux River Bridge.
¨
E-80
and Osmose are both continuing between Elkton and Wolsey on RRIF bridges,
although progress has been somewhat slowed by the lack of track windows. We are
able to progress work items that do not require a track window or outage.
Current traffic requirements have necessitated deferring some of the work for a
couple of weeks. These temporary work deferral periods were planned for during
the different harvest or heavy rail traffic rush periods. These temporary
deferrals should not affect our ultimate schedule.
¨
The
Sioux River Bridge is being worked on by E-80.
Prep work began on March 15th and on April 12th
they started driving piling with 36 of 78 pilings being driven thus far. This
completes the pile driving that is required for the east end of the
bridge. For the next two months the
crew will be working on the concrete caps and abutments, which will be poured
in place. The first of these concrete caps was poured on Wednesday May 26th
and all but one of these concrete caps in the east approach span has been
completed. The crew will complete the
east end of the bridge by the first of August before they travel to the west
side to start the other half of this project.
This week we began to change out the spans on the east approach. Two
spans and the truss ballast tub interface have been completed. Span Changeout
should continue through the next week provided traffic will permit track
windows. This project is on schedule and should be completed by November 1,
2004.
¨
The
pile driving crane is currently enroute to the DM&E, so the Cottonwood and
Mine Creek bridges are on schedule to begin in early July and completed in late
August or early September.
¨ Two bridges have been completed this week, one near MP 397 and the other near MP 356.