Bridges
Weekly Update #16
28
July 2004
ON SCHEDULE
Of
the 146 bridges scheduled to be repaired this year, we are completed with 55 of
them, and 7 more are currently works-in-progress as of July 28th. All
bridgework is proceeding on schedule to be completed by November 2004. Span change out is complete on the east end
of the Sioux River Bridge.
¨
E-80
and Osmose are both continuing between Verdi and Garvin on RRIF bridges.
¨
The
Sioux River Bridge is being worked on by E-80.
Prep work began on March 15th and on April 12th
they started driving piling with 36 of 78 pilings being driven thus far. This
completes the pile driving that is required for the east end of the
bridge. For the next two months the
crew was working on the concrete caps and abutments, which were poured in
place. The first of these concrete caps was poured on Wednesday May 26th and
all of these concrete caps in the east approach span have been completed. The crew completed the final touches on the
east end of the bridge this week. The crane is moved to the west side and
started pile driving on the west approach span yesterday. This project is on schedule and should be
completed by November 2004.
¨
Tthe
ballast tubs deck renewal for Br# 502 at MP 196.7 is in progress, 12 of the 22
ballast tubs were changed-out as of today or approximately a half of this
bridge deck is completed.
¨ The four bridges completed this week were located on the PRC Subdivision at MP 536.6 and on the Huron Subdivision at MP 272.8, MP 267.9 and MP 267.1.