Bridges
Weekly Update #25
29
September 2004
ON SCHEDULE
Of
the 146 bridges scheduled to be repaired this year, we are completed with 115
of them, and 8 more are currently works-in-progress as of Sept. 29th. All
bridgework is proceeding on schedule to be completed by November 2004. Currently within the RRIF project area only
24 bridges still require work to be completed.
¨
Bridge
Repair is continuing between Verdi to Garvin and Sleepy Eye to Tracy on RRIF
bridges. Currently only 3 bridges
remain to be completed between Huron and Verdi (287.0, 287.3, & 295.5) not
including the Big Sioux River Bridge. Between Verdi and Tracy there are 15 bridges left to finish and
between Tracy and Sleepy Eye there are only 5 bridges remaining to be
completed.
¨
The
Sioux River Bridge is nearing completion worked on by E-80. Prep work began on March 15th and
on April 12th they started driving piling. E-80 completed the pile
driving that is required for the entire bridge a total of 78 piling have been
driven. The crew has completed all of
the concrete caps and abutments, which are poured in place. Concrete deck tubs
have been completed. The only remaining
work will be the walkways, cleanup and other finishing touches. This project is
on schedule and should be completed by November 2004.
¨
The
work at Bridge 526, MP 206.2 is underway reconstructing the pier under the west
approach span and other associated work. All the pile driving is completed and work is continuing.
¨
One
bridge upgrade was started on the PRC at MP 532.9 a substantial amount of work,
which will include new deck and stringer chords. This work is still in
progress, not yet complete.
¨ There were 2 bridges completed this week. They were located on the Huron sub (2 bridges completed between Verdi and Balaton).