Bridges
Weekly Update #27
13
October 2004
ON SCHEDULE
Of the 146 bridges
scheduled to be repaired this year, we are completed with 119 of them, and 21
more are currently works-in-progress as of Oct. 13th. All bridgework is proceeding on schedule to be
completed by November 2004. Currently
within the RRIF project area only 23 bridges still require work to be completed.
¨ Bridge
Repair is continuing between Verdi to Garvin and Sleepy Eye to
¨ Osmose will complete their work on this project this Friday; the remaining work will be completed by E-80 and DM&E Forces.
¨ As of this writing all the remaining work on the bridges in the RRIF project area are principally decks and headwalls, although completion of this work is still important it does not affect the bridges load carrying capacity. This means that all our bridges between Sleepy Eye and Wolsey in the RRIF project area can now handle 286K loading, and the remaining work will still be completed on schedule.
¨ The
¨ The work at Bridge 526, MP 206.2 is underway reconstructing the pier under the west approach span and other associated work. All the pile driving is completed and work is continuing.
¨ One bridge upgrade was started on the PRC at MP 532.9, a substantial amount of work, which will include new deck and stringer chords. This work is still in progress, not yet complete.
¨ There
were 3 bridges completed this week. One
located near