Bridges
Weekly Update #28
20
October 2004
ON SCHEDULE
Of the 146 bridges
scheduled to be repaired this year, we are completed with 120 of them, and 20
more are currently works-in-progress as of Oct. 20th. All RRIF bridgework is
proceeding on schedule to be completed by November 2004. Currently within the RRIF project area only
21 bridges still require work to be completed.
¨ Bridge
Repair is continuing between Verdi to Garvin and Sleepy Eye to
¨ Osmose completed their work on this project last Friday; the remaining work will be completed by E-80 and DM&E Forces.
¨ As of this writing all the remaining work on the bridges in the RRIF project area are principally decks and headwalls, although completion of this work is still important it does not affect the bridges load carrying capacity. This means that all our bridges between Sleepy Eye and Wolsey in the RRIF project area can now handle 286K loading, and the remaining work will still be completed on schedule.
¨ The
¨ The work at Bridge 526, MP 206.2 is underway reconstructing the pier under the west approach span and other associated work. All the pile driving is completed and work is continuing.
¨ One bridge upgrade was started on the PRC at MP 532.9 a substantial amount of work, which will include new deck and stringer chords. This work is still in progress, not yet complete.
¨ There were 1 bridge completed this week on the DM&E between Sleepy Eye and Tracy.