Rail
Weekly Update #4
6
May 2004
AHEAD OF SCHEDULE
As of May 6, we have installed just over 25 miles of the roughly 97 track miles scheduled to be completed by November 19th. As of now, it appears we will meet or beat that schedule. The RJ Corman crew returned to the Volga area on May 1st and started laying rail between MP 298 and Arlington on Sunday the 3rd. We expect this 10 mile section to be completed on or before Saturday the 15th with the Arlington to Lake Preston section will be completed by months’ end.
¨
RJ
Corman began the second section of CWR, which runs between Volga and Lake
Preston, on May 2nd and now expect to have this area completed by
the end of May. This section totals over 20 track miles of CWR.
¨
When
this section is completed, we will do some spot tie installation and spot
surfacing and increase the speed from the current 10 mph to between 20 and 30
mph. When final tie installation and surfacing are completed this will be 40
mph.
¨
Total
rail delivered thus far is 63 track miles.
¨
The
remaining 5 rail trains (390,000 feet) are scheduled to be here by June 30,
2004.
¨
This
week we received another rail train, CWR train #6, which was unloaded on Monday
the 3rd of May and we expect to receive train # 7 during the third
week of May. Engineering forces in the Davenport area also unloaded 14 strings
of 115# CWR in the Buffalo area during the week from a train which had more
rail on it destined for another property.