Rail
Weekly Update #9
10
June 2004
CWR PROGRESS CONTINUES
As of June 10th, we have installed just over 50 of the roughly 97 track miles scheduled to be completed by November 19th. It appears we will meet or beat that schedule. The RJ Corman crew that has been laying all of the CWR on the DM&E, returned to the area and began laying rail at MP 235.5 on Friday the 4th. They will continue laying rail, seven days a week, thru the 25th of June and we expect to have rail laid to MP 257 by that time. We now expect the CWR on the DM&E to be completed by July 15th. The CWR on the Mason City sub of the IC&E is to be completed by late July or early August with the curve replacement program being completed in late November.
¨
Tie
work is completed on the first stretch of CWR between Springfield and Sleepy
Eye and ballast has been dumped in preparation for final surfacing and raising
of speed in this area to 40 MPH. We
expect this area to be completed by mid to late July.
¨
Spot
surfacing, bridgework and tie work are continuing on the second stretch of CWR
between Volga and Lake Preston and we expect this entire area to be up to 25 MPH
by the July 4th holiday weekend. This area had been 10 MPH since
early 1997.
¨
The
remaining 3 rail trains (230,000 feet) are scheduled to be here by the second
week of July. These last three rail trains will all be unloaded on the
IC&E, 2 for the Calmar project and the other for the 2004 curve
program. The next rail train to be
unloaded is scheduled to be pulled from the Pueblo welding plant on June 14th
and should be arrive Kansas City around the 18th with unloading
scheduled for Calmar around Monday the 21st of June.
¨
Rail
laying on the Calmar project is now expected to begin after the 4th
of July to allow for the installation of all of the ties and the switches.
¨
The
IC&E curve patch program, under the direction of foreman Steve Koser and
Project Supervisor Tom Goffinet, expects to start their part of the 2004 CWR
project on the IC&E the second week of July on the Mason City sub and will
lay curve patch rail for the remainder of the year toward Kansas City.