Rail Weekly Update #19

19 August 2004

 

 

 

IC&E CWR PROJECTS MAKING GOOD PROGRESS

 

 

As of August 19th, we had installed just over 81 of the roughly 97 track miles to be completed by November 19th.   It appears we will meet or beat that schedule.  The LA Colo crew began installing CWR on the IC&E near Calmar, Iowa last week and will expect to complete that 15 track miles by early Labor Day.  The IC&E CWR crew, under foreman Steve Koser’s guidance, also began installing about 9 track miles of CWR on curves across the entire IC&E system this week and will install rail nearly through the end of the year. Mr. Koser’s crew has completed the Mason City sub portion of the curve project and will complete the Marquette sub portion this week and Chicago sub portion next week.

 

 

 

¨       All tie, crossing, and bridge work is completed on the first stretch of CWR between Sleepy Eye and Springfield and final surfacing will be coordinated with the completion of the Cobden siding. 

¨       All tie work has been completed on the second stretch of CWR between Volga and Lake Preston and ballast is being dumped in preparation for final surfacing which began last week.  Mr. Ruckdaschal’s crew is expected to complete the surfacing over the next several weeks.

¨       Work will continue on crossings on the last section of CWR between Garvin and Verdi over the next several weeks.  Along with that there will be several cranes in the area cleaning up scrap rail and OTM as well as the salvageable material.

¨       The last remaining rail train for this year’s projects (80,000 feet) just arrived in Kansas City yesterday, the 18th, and is traveling toward the Calmar area for unloading later this week or this weekend.