Rail
Weekly Update #20
26
August 2004
IC&E CWR PROJECTS
MAKING GOOD PROGRESS
As of August 26th, we had installed just over 84 of the roughly 97 track miles to be completed by November 19th. It appears we will meet or beat that schedule. The LA Colo crew began installing CWR on the IC&E near Calmar, Iowa last week and will expect to complete that 15 track miles by early September. The IC&E CWR crew, under foreman Steve Koser’s guidance, also began installing about 9 track miles of CWR on curves across the entire IC&E system this week and will install rail nearly through the end of the year. Mr. Koser’s crew has completed the Mason City sub portion of the curve project and the Marquette sub portion last week and will complete the Chicago sub portion today, the 26th of August. The Koser crew is nearly 1/3rd done with their portion of the 2004 CWR project.
¨ All tie, crossing, and
bridge work is completed on the first stretch of CWR between Sleepy Eye and
Springfield and final surfacing will be coordinated with the completion of the
Cobden siding which is now expected to be completed by the second full week of
September.
¨
Chad
Roob’s crossing gang has been busy completing the crossings on the Volga to
Lake Preston portion of the CWR project and has nearly completed these
crossings. When this is completed, this
crew will finish all of the crossings on the last stretch of CWR between Garvin
and Verdi. Earl Ruchdaschael’s surfacing
crew has been assisting in this crossing effort as well as doing out of face surfacing
in the area.
¨
Mike
Anderson is overseeing the effort as we continue to use several cranes to clean
up the OTM and scrap rail in the last stretch of CWR on the DM&E between
Garvin and Verdi.
¨
The
last remaining rail train for this year’s projects (80,000 feet) was unloaded
on Monday the 23rd in the Calmar area.
¨
Welding
crews are making all of the closure welds and the welds in all of the switches
and should complete all of the welding on the Calmar project within a week
after the completion of the CWR laying.
¨
Randy
Parmenter’s crossing gang has been extremely busy installing crossing in the
Calmar CWR area in preparation for the completion of the entire project. Remington Hills’ surfacing crew has been
assisting this effort
¨
The
clean up effort on the Calmar CWR is just beginning and will be completed in
front of the final surfacing.