Rail
Weekly Update #20
2
September 2004
IC&E CWR PROJECTS
MAKING GOOD PROGRESS
As of September 2, we had installed just over 86 of the roughly 97 track miles to be completed by November 19th. It appears we will meet or beat that schedule. The LA Colo crew began installing CWR on the IC&E near Calmar, Iowa in early August and we expect them to complete that 15 track miles by early September. The IC&E CWR crew, under foreman Steve Koser’s guidance, also began installing about 9 track miles of CWR on curves across the entire IC&E system this week and will install rail nearly through the end of the year. Mr. Koser’s crew has completed the Mason City sub portion and the Marquette sub portion of the curve project two weeks ago. They completed the Chicago sub late last week and will be on the River sub for the most of September. The Koser crew is over 1/3rd done with their portion of the 2004 CWR project.
¨
All
tie, crossing, and bridge work is completed on the first stretch of CWR between
Sleepy Eye and Springfield and final surfacing will be coordinated with the
completion of the Cobden siding which is now expected to be completed by the
second full week of September.
¨
Chad
Roob’s crossing gang has completed all of the paved crossings on the second
stretch of CWR on the DM&E, and will now assist Earl Ruckdaschel’s
surfacing crew with the gravel crossings.
¨
Mike
Anderson is overseeing the effort as we continue to use several cranes to clean
up the OTM and scrap rail in the last stretch of CWR on the DM&E between
Garvin and Verdi.
¨
The
last remaining rail train for this year’s projects (80,000 feet) was unloaded
on Monday the 23rd in the Calmar area.
¨
Welding
crews are making all of the closure welds and the welds in all of the switches
and should complete all of the welding on the Calmar project within a week
after the completion of the CWR laying.
¨
Randy
Parmenter’s crossing gang has been extremely busy installing crossings in the
Calmar CWR area in preparation for the completion of the entire project.
Remington Hills’ surfacing crew has been assisting this effort.
¨
The
clean up effort on the Calmar CWR is just beginning and will be completed in
front of the final surfacing.