Rail
Weekly Update #26
14
October 2004
CWR PROJECTS OVER 95%
COMPLETED!!!!
As of October 14 we have installed just over 93 of the roughly 97 track miles to be completed by November 19th.
No CWR was laid last week since
the IC&E’s crew is still installing ties, however, we do expect the CWR
curve program to get rolling again early next week just south of
We continue to work on the
surfacing in the CWR areas on both properties to get those areas up to 40 MPH
by freeze up and in fact have completed two of the three areas on the DM&E
and are about finished the Calmar project on the IC&E. When the DM&E project is completed, the
running time from Huron to
¨ Chad Roob’s crossing gang continues
to renew crossings in conjunction with Kent Maxon’s surfacing crew.
¨ Mike Anderson, who in his
normal job is the section foreman at Tracy Minnesota, has done an excellent job
working with Mark Trudeau and coordinating all of the crews on the
¨ Randy Parmenter’s crew has
completed all of the crossings on the Calmar CWR project and will spend the
remainder of the season on clean up and other crossing projects on the IC&E
“corn” lines.
¨ The clean up effort on the
Calmar CWR is near completion and will be completed in front of the final
surfacing which is scheduled to be completed by the end of October.
¨ Bledsoe Rail Service is
doing the closure welds on the DM&E projects and Railtech crews are doing
the closure welds on the IC&E.