Rail Weekly Update #29

4 November 2004

 

 

 

CWR PROJECTS OVER 95% COMPLETED!!!!

 

 

As of  November 4 we have installed just over 94 of the roughly 97 track miles to be completed by November 19th. 

Steve Koser’s crew has laid rail on several curves and will continue this project until mid December on the Kansas City sub.

 We continue to work on the surfacing in the CWR areas on both properties to get those areas up to 40 MPH by freeze up and have completed two of the three areas on the DM&E and are about finished with the Calmar project on the IC&E.  When the DM&E project is completed the run time from Huron to Tracy will have been reduced from nearly 10 hours to just over 4 hours!!

 

¨       Chad Roob’s crossing gang continues to renew crossings in conjunction with Kent Maxon’s surfacing crew.

¨       Mike Anderson, whose normal job is the section foreman at Tracy, Minnesota, has done an excellent job working with Mark Trudeau and coordinating all of the crews on the Tyler project. 

¨       Randy Parmenter’s crew has completed all of the crossings on the Calmar CWR project and will spend the remainder of the season on clean up and other crossing projects on the IC&E “corn” lines.

¨       The clean up effort on the Calmar CWR is near completion and will be completed in front of the final surfacing.

¨       Bledsoe Rail Service is doing the closure welds on the DM&E projects and Railtech crews are doing the closure welds on the IC&E.