4
November 2004
CWR PROJECTS OVER 95%
COMPLETED!!!!
As of November 4 we have installed just over 94 of the roughly 97 track miles to be completed by November 19th.
Steve Koser’s crew has laid rail on several
curves and will continue this project until mid December on the
We
continue to work on the surfacing in the CWR areas on both properties to get
those areas up to 40 MPH by freeze up and have completed two of the three areas
on the DM&E and are about finished with the Calmar project on the
IC&E. When the DM&E project is
completed the run time from Huron to
¨ Chad Roob’s crossing gang
continues to renew crossings in conjunction with Kent Maxon’s surfacing crew.
¨ Mike Anderson, whose normal
job is the section foreman at
¨ Randy Parmenter’s crew has
completed all of the crossings on the Calmar CWR project and will spend the
remainder of the season on clean up and other crossing projects on the IC&E
“corn” lines.
¨ The clean up effort on the
Calmar CWR is near completion and will be completed in front of the final
surfacing.
¨ Bledsoe Rail Service is
doing the closure welds on the DM&E projects and Railtech crews are doing
the closure welds on the IC&E.