11
November 2004
CWR PROJECTS OVER 95%
COMPLETED!!!!
As of November 11 we have installed just over 95 of the roughly 97 track miles to be completed by November 19th.
Steve Koser’s crew has laid rail on several
curves and will continue this project until mid December on the
Surfacing continues on the last two CWR
locations and we expect both of those to be completed by the end of this week
or middle of next week. These areas, one
on the IC&E near
On the DM&E, the final surfacing on the
¨ Chad Roob’s switch & crossing
gang is installing the Tracy cross overs this week and will then install a new
switch and track for Barti Metal at Huron to conclude their year.
¨ Rik Hanson has been
supervising the installation of four switches and the building of several
hundred feet of connecting track at
¨ Bledsoe Rail Service is
doing the closure welds on the DM&E projects.
¨ Railtech crews are doing the
closure welds on the IC&E.