18
November 2004
CWR PROJECTS OVER 95%
COMPLETED!!!!
As of November 18 we have installed just over 95 of the roughly 97 track miles we now expect to be completed by early December
Steve Koser’s crew has laid rail on several
curves and will continue this project until mid December on the
Surfacing should be completed on the last two
CWR locations this week and these areas, one on the IC&E near
On the DM&E, the
Engineering managers on both properties are now in the final stages of clean up from the 2004 CWR projects and are also preparing for next year’s possible program. The preliminary plan for 2005 is to lay approximately 15 track miles of CWR on each property with one additional trainload for curve projects on the IC&E, although we must stress this is very preliminary.
¨ Chad Roob’s switch &
crossing gang installed the Tracy cross overs late last week and will install a
new switch and track for Barti Metal at Huron to conclude the year’s projects
for this crew
¨ Rick Hanson has been
supervising the installation of four switches and the building of several
hundred feet of connecting track at
¨ Bledsoe Rail Service is
doing the closure welds on the DM&E projects.
¨ Railtech crews are doing the
closure welds on the IC&E.