Sidings
Weekly Update #4
6
May 2004
SCHEDULES FIRMING, BUT NOT COMPLETED
As
of May 6, we have put 1 of the 4
sidings tentatively planned for 2004 in to service although it is not
completely finished.
1.
The Cobden siding construction began on April 27, and thanks to some
excellent weather, has progressed to the point of being 80% complete. We are now awaiting final approval for our
wetlands proposal, but at any rate we now expect this siding to be in service
by mid- September. If the approval process is delayed, we may shorten the
siding to 8000’ to get it in service prior to the grain rush.
¨
Switches
are ordered and expect delivery and installation of the West switch before June
15th
¨
Ties
are ordered and will be delivered to the sight over the next three weeks
¨
OTM
and rail is being recovered from the CWR project near Volga and will be
transported to the sight during the next two weeks
2.
The Tracy siding is ahead of its scheduled May 15 date for being put in
to service.
¨
Sub
grade is 100% complete and the track is over 95% complete
¨
The
Tracy Siding will be put into service at 1700 on the 6th of May.
This is over a week ahead of schedule and should help with congestion problems
in the area.
¨
Crossing
at Sale Barn Road was completed on May 5th and final surfacing of
the siding will be done by the crew of Kent Maxon on Thursday the 6th.
¨
We
expect to install the crossovers later in May or June to complete the project,
but the new pass will be usable without the crossovers being installed.
3.
The negotiations on the Florence siding appear to be making better
progress this past week, but we are still awaiting a final agreement with BNSF
before we can commit.
4. The internal discussions regarding the Manchester siding are leaning toward not building it if Florence happens. Instead, we are looking at other alternatives, including extending De Smet and Elkton as well as extending and rebuilding the Sanborn siding. Any ideas or suggestions from the field as to other potential siding locations (extensions or new sidings) would be much appreciated. Operational needs are the primary consideration. Suggestions should be directed to Dick Awe or Steve Scharnweber.