Sidings
Weekly Update #5
13
May 2004
SCHEDULE CHANGE; TWO MORE SIDINGS ADDED ONE,
MORE BEING CONSIDERED
As
of May 13, we have put 1 of the 5 sidings now tentatively planned for 2004 into
service although it is not completely finished.
1.
The Cobden siding construction began on April 27, and thanks to some
excellent weather, has progressed to the point of being 80% complete. We are now awaiting final approval for our
wetlands proposal, but at any rate we now expect this siding to be in service
by late August. If the approval process is delayed, we may shorten the siding
to 8000’ to get it in service prior to the grain rush.
§
Switches
are ordered and expect delivery and installation of the west switch before June
15th
§
Tie
delivery started this week and will continue thru the next three weeks.
§
The
first two cars of rail have been shipped from Volga to the Sleepy Eye area for
this project and one car of OTM has
also been loaded and shipped. This material is being recovered from the Volga
CWR project
2.
The Tracy siding was put in service on Thursday the 6th and
has provided immediate relief to traffic congestion in the area.
§
We
expect to install the crossovers later in June to complete the project, but the
new pass is usable without the crossovers being installed.
§
The
length of the new passing track is over 8000’
§
After
the completion of the siding, the reconfiguration of the Tracy yard allowed
transportation to have track 4 which can hold 60 cars.
3.
The negotiations on the Florence siding appear to be making better
progress this past week, but we are still awaiting a final agreement with BNSF
before we can commit.
4. After receiving many suggestions from the
field we have decide not to build the Manchester Siding this year. Instead we will rebuild the Sanborn siding
and extend Elkton. We are also considering an extension at DeSmet.
5.
The Elkton Siding will be extended over 4000’ to the east and will help
with congestion and will enable the meeting of longer trains.
§
Dirt
work will start immediately and will expected to be completed by the end of May
§
A
new switch for east end is on order and will be delivered by the end of June.
§
Tie
options are being considered and a firm order is expected to be made by Friday
the 21st
§ Rail and OTM will be recovered from the Volga / Lake Preston CWR project and will be delivered to the location.
§ Best estimate now for being in service is mid to late August.
4. The Sanborn Siding project involves renewing over ½ the ties in
the current siding and changing the rail as well as adding ballast and
surfacing.
§ Ties are ordered and will be delivered by the end of the month
§ Expect contractor LA Colo to install these ties when his crews are in the area around mid June
§ Will replace rail as soon as ties are installed
§ Ballast and surfacing will be completed after rail and expect this project to be completed by the end of July, depending on manpower issues.
6. We are currently doing a new evaluation at
DeSmet and preparing new estimates to extend that siding to the west about
3700’. The decision on the DeSmet Siding will be made by the end of the
month