Sidings
Weekly Update #12
1
July 2004
Great strides being made on Siding Projects
As
of July 1st, we have put 2 of the 6 sidings now planned for 2004
into service, Tracy and Sanborn.
1.)
The Cobden siding track work has now started!!! Track work is now about 20% toward
completion!!
¨
The
west switch was installed on June 23rd by New Ulm section and
surfaced by Kent Maxon’s surfacing crew the next day.
¨
Track
construction started on June 28th with over 2000 ties being laid out
on the grade already and over 1000 track feet of rail laid on the ties.
¨
Darrin
Legare from New Ulm is heading up the rail laying on this project with the help
of 5 other employees from Wes Risseeuw’s tie gang and boom truck operator Ted
Arndt.
¨
This
siding is expected to be a total of 10,000 feet, if we can get the wetlands issue
settled on the east end of the project area.
If we have not reached a satisfactory resolution to the wetlands issue
within the next few weeks, we will shorten the siding length to around 8000
track feet to get this siding into service prior to the grain rush.
2.)
The Tracy siding was put into service on Thursday the 6th of
May and continues to perform up to the transportation department’s
expectations.
¨
To
complete the project, we expect to install the crossovers late July or more
likely in August, but the new pass is usable without the crossovers being
installed and has been used extensively to meet trains.
3.)
The negotiations on the Florence siding continue to move forward and we
expect a final agreement very soon. We
still expect to receive an agreement soon enough to complete this project
during this work season.
4.) The De Smet Siding extension was
approved in late May. This project will
extend the siding nearly 4,000’ westward from the current west switch location.
·
The
contractor selected to do the dirt work is Loiseau of Flandreau South Dakota.
·
The
switch has been delivered to the site this past week and will be assembled in
the near future.
·
Switch
installation and track construction are scheduled to begin shortly after the
completion of the dirt work.
·
Rail
and OTM have been recovered from the Arlington CWR project and were delivered
to the site during the past week.
5.)
The Elkton Siding will be extended over 4,000’ to the east. This will help with congestion and will
enable the meeting of longer trains.
·
Dirt
work has been completed for some time awaiting the track construction.
·
A
new switch for the east end has been delivered to the site and will be
assembled and installed within the next couple weeks.
·
Ties
have been received and will be unloaded on site within the next several days.
·
Rail
and OTM that has been recovered from the Volga/Lake Preston and the Tyler
projects will be delivered and stored on site ready for the construction.
6.) The
Sanborn Siding project involved renewing over ½ the ties in the current
siding and elevator tracks and changing the rail as well as adding ballast and
surfacing to remove restrictions that allowed only empty cars and four-axle
locomotives to use these tracks. The
track was put into service on June 23rd!!
· Ties were installed the week of the 14th of June.
· Rail was changed and anchors installed the week of June 21st.
· Ballast will be unloaded and surfacing will be completed within the next couple weeks.