Sidings
Weekly Update #17
5
August 2004
ELKTON EXTENSION COMPLETED!!
DE SMET EXTENSION AND FLORENCE CONNECTION BOTH STARTED!!
As
of August 5th we
have put 3 of the 6 sidings now planned for 2004 into service, Tracy, Sanborn
and Elkton. Work on the other three;
Cobden, Florence and De Smet is progressing.
1.)
The Cobden siding track work is now about 70% complete if we assume that
we are going to be able to build the entire 10,000 foot siding.
¨ Track construction started
on June 28th. Over 7,000
foot of track has been completely built
¨
Siding
has been put into service as a 4,500 foot stub track until final extension is
completed .
¨
Wetlands
mitigation is in its final stages and we expect to have the work on this siding
beginning again by the middle of the month.
2.)
The Tracy siding was put into service on Thursday May 6th and
continues to perform up to the transportation department’s expectations.
¨
We
have received the crossover switches this week and will install them in late
August or early September when the surfacing crew gets close to the area.
3.)
The negotiations on the Florence siding have finally been settled and
signed so construction can begin.
¨
The
dirt work contract has been awarded to Mathiowetz Construction of Sleepy
Eye. Work started on August 2nd and we
expect it to be completed by the end of September.
¨
Connection
is expected to be in service by the end of October.
4.) The De Smet Siding extension was
approved in late May. This project will
extend the siding nearly 4,000 feet westward from the current west switch
location.
·
The
dirt work started on Monday the 26th and will be completed by the
end of this week.
·
The
new west switch has been assembled and is being installed today, the 5th
of August, by Wes Risseeuw and his crew.
·
Track
construction is expected to begin next week and be completed in three weeks.
·
The
new siding is expected to be in service by the 20th of August.
5.)
The Elkton Siding has been extended over 4,000 feet to the east and was
put into service on the 28th of July. This will help with congestion and will enable the meeting of
longer trains.
6.) The
Sanborn Siding project involved renewing over ½ the ties in the current
siding and elevator tracks and changing the rail as well as adding ballast and
surfacing. This removed restrictions
that allowed only empty cars and four-axle locomotives to use these
tracks. The track was put back into
service on June 23rd!!
· Ties were installed the week of June 14th.
· Rail was changed and anchors installed the week of June 21st.
· Surfacing has been completed so this project is 100% complete.