Sidings
Weekly Update #23
23
September 2004
5 New
sidings now in service!!!
As
of September 23rd we have put 5 of the 6 sidings now planned for 2004 into
service. They are Tracy, Sanborn, Elkton, De Smet and now Cobden.
1.)
The Cobden siding track work is now over 100% complete.
¨
The
siding was put into “full” service as a 9900’ siding on Thursday the 16th
¨
This
siding, the longest on the DM&E, had final surfacing completed by Kent
Maxon’s crew earlier this week
2.)
The Tracy siding was put into service on Thursday May 6th and
continues to perform up to the transportation department’s expectations.
¨
The
cross-over switches will be assembled in late September and installed later in
the year when we have a surfacing crew close to the area.
3.)
The Florence siding construction is on schedule for completion by the
end of October.
¨
Mathiowetz
Construction of Sleepy Eye started on their portion of the dirt work on August
2nd and completed the connection portion in late August. All dirt work is 100% completed.
¨
Material
continues to arrive on site and crew’s headed up by Wes Risseeuw have been busy
building the connection and distributing material in the siding area in
anticipation of starting construction there later this week
¨
The
connection and siding are expected to be in service by the end of October.
¨
The
first 4 switches were inspected earlier in Seattle and have been delivered to
the site.
¨
The
connection switch to the DM&E main line at MP 247.8 was installed on Monday
the 13th and the “wye” switch on the connection track was assembled
in place on Friday the 10th.
4.) The De Smet Siding extension was
put into service on the 20th of August.
¨
This
extension is now 100% completed
5.)
The Elkton Siding has been extended over 4,000 feet to the east and was
put into service on the 28th of July. This has helped with congestion and will enable the meeting of
longer trains. Total length of Elkton
siding is now 8200’.
¨ Extension is 100% completed!!!
6.) The Sanborn Siding project involved renewing over ½ the ties in the current siding and elevator tracks and changing the rail as well as adding ballast and surfacing. This removed restrictions that allowed only empty cars and four-axle locomotives to use these tracks. The track was put back into service on June 23rd!!
¨ Project is 100% completed!!!