Sidings
Weekly Update #25
7
October 2004
LAST SIDING PROJECT,
As
of October 7 we have put 5 of the 6 sidings now planned for 2004 into service.
They are Tracy, Sanborn, Elkton, De Smet and Cobden.
1.)
The Cobden siding track work is now 100% complete.
¨ The siding was put into
“full” service as a 9900’ siding on Thursday the 16th of September.
2.)
The
¨ The cross-over switches will
be assembled in late September and installed later in the year when we have a
surfacing crew close to the area.
3.)
The
¨ Mathiowetz Construction of
Sleepy Eye is 100% completed on the dirt work for the entire project
¨ The 4 switches have been
delivered to the site.
¨ The connection switch to the
DM&E main line at MP 247.8 was installed on Monday the 13th and
the “wye” switch on the connection track was assembled in place on Friday the
10th.
¨ The Connection track is
built to the wye track switch and ballast has been dumped on this track. Kent
Maxon’s surfacing crew with Jerry Ziemke running the 6700 tamper have made one
surfacing pass through the area
¨ Wes Risseeuw’s tie crew,
assisted by crane operator Lynn, Boom Truck operators Danburg and Kellar and
contractor Dave Moriarty, are now working on the siding track at
¨ Chad Roob’s switch and
crossing crew is assembling both switches for the
4.) The De Smet Siding extension was
put into service on the 20th of August.
¨
This extension is now 100% completed
5.)
The Elkton Siding has been extended over 4,000 feet to the east and was
put into service on the 28th of July. This has helped with congestion and will
enable the meeting of longer trains.
Total length of Elkton siding is now 8200’.
¨ Extension is 100% completed!!!
6.) The Sanborn Siding project involved renewing over ½ the ties in the current siding and elevator tracks and changing the rail as well as adding ballast and surfacing. This removed restrictions that allowed only empty cars and four-axle locomotives to use these tracks. The track was put back into service on June 23rd!!
¨ Project is 100% completed!!!