Sidings
Weekly Update #28
28
October 2004
As
of October 21, we have put all 6 sidings planned for 2004 capital program into
service. The 6th and last
siding was put into service Friday, the 15th. The new sidings and extensions are
1.)
The Cobden siding track work is now 100% complete.
¨ The siding was put into
“full” service as a 9900’ siding on Thursday the 16th of September.
2.)
The
¨ Chad Roob’s crew has
assembled the cross-over switches and we expect to install them within the next
couple weeks.
3.)
The
·
Siding is 95% completed with only the closure welds left to finish.
This welding work is being done by Bledsoe Welding Services and should be
completed by the end of the month.
·
The BN connection portion of the
4.) The De Smet Siding extension was
put into service on the 20th of August and extends the siding more
than 3000 feet to the west.
¨
This extension is now 100% completed!!!
5.)
The Elkton Siding has been extended over 4,000 feet to the east and was
put into service on the 28th of July. This has helped with congestion and will
enable the meeting of longer trains.
Total length of Elkton siding is now 8200’.
¨ Extension is 100% completed!!!
6.) The Sanborn Siding project involved renewing over ½ the ties in the current siding and elevator tracks and changing the rail as well as adding ballast and surfacing. This removed restrictions that allowed only empty cars and four-axle locomotives to use these tracks. The track was put back into service on June 23rd!!
¨ Project is 100% completed!!!