Sidings
Weekly Update #30
11
November 2004
As
of November 11th we have put all 6 sidings planned for 2004 capital
program into service. The new sidings
and extensions are
1.)
The Cobden siding track work is now 100% complete.
¨ The siding was put into
“full” service as a 9,900’ siding on Thursday the 16th of September.
2.)
The
¨ Chad Roob’s crew is
installing the crossover switches this week. This will enable crews to switch
the “dc” yard without blocking the pass. When the cross over project is completed,
the
3.)
The
·
Siding is 95% completed with only the closure welds left to finish.
This welding work is being done by Bledsoe Welding Services and should be
completed by the end of the month.
·
The BN connection portion of the
4.) The De Smet Siding extension was
put into service on the 20th of August and extends the siding more
than 3,000 feet to the west.
¨
This extension is now 100% completed!!!
5.)
The Elkton Siding has been extended over 4,000 feet to the east and was
put into service on the 28th of July. This has helped with congestion and will
enable the meeting of longer trains.
Total length of Elkton siding is now 8,200’.
¨ Extension is 100% completed!!!
6.) The Sanborn Siding project involved renewing over ½ the ties in the current siding and elevator tracks and changing the rail as well as adding ballast and surfacing. This removed restrictions that allowed only empty cars and four-axle locomotives to use these tracks. The track was put back into service on June 23rd!!
¨ Project is 100% completed!!!