Sidings
Weekly Update #31
18
November 2004
As
of November 18th we have put all 6 sidings planned for 2004 capital
program into service. The new sidings
and extensions are
1.)
The Cobden siding track work is now 100% complete.
¨ The siding was put into
“full” service as a 9,900’ siding on Thursday the 16th of September.
2.)
The
¨ The installation of the
cross-overs has completed this project
3.)
The
·
Siding and connection are virtually 100% completed with only a few
field welds left to do.
4.) The De Smet Siding extension was
put into service on the 20th of August and extends the siding more
than 3,000 feet to the west.
¨
This extension is now 100% completed!!!
5.)
The Elkton Siding has been extended over 4,000 feet to the east and was
put into service on the 28th of July. This has helped with congestion and will
enable the meeting of longer trains.
Total length of Elkton siding is now 8,200’.
¨ Extension is 100% completed!!!
6.) The Sanborn Siding project involved renewing over ˝ the ties in the current siding and elevator tracks and changing the rail as well as adding ballast and surfacing. This removed restrictions that allowed only empty cars and four-axle locomotives to use these tracks. The track was put back into service on June 23rd!!
¨ Project is 100% completed!!!