Surfacing
Weekly Update #1
16
April 2004
ON SCHEDULE
To date, we have surfaced 23 of the 800 pass
miles to be surfaced in 2004, scheduled to be completed by November 24th. As of now, it appears we will meet that
schedule. The surfacing is on track,
greatly aided by the acquisition of (a) 53 air dump ballast cars to supplement
our existing fleet and (b) a new Brandt truck which can pull up to 25 cars of
ballast.
¨
53
new Ballast cars were leased for 2 years.
¨
Surfacing
started March 17, 2004 on the west end of DM&E.
¨
As
of April 15, 2004 7,500 tons (100 car loads) of ballast has been
delivered.
¨
23
pass miles have been surfaced.