Surfacing Weekly Update #8

3  June 2004

 

 

 

CONTINUING ON SCHEDULE

 

As of 3 June, we have surfaced over 170 of the 800 pass miles to be surfaced in 2004, scheduled to be completed by November 24th.  As of now, it appears we will meet that schedule. 

 

¨       All of the 53 new Ballast cars that were leased for 2 years have arrived on line and are in service. The general consensus of the engineering forces is that these cars are an excellent investment and allow increased efficiency of the ballast unloading process.

¨       The Brandt truck, operated by Ernie Lehmkuhl has been very instrumental in the ballast unloading operation. This truck can pull up to 20 cars of ballast or other material for MOW crews to unload saving on work train requirements and increasing the flexibility of the MOW forces.

¨       Surfacing continues at a very strong pace with over 25 miles completed last week and averaging over 20 miles per week.  We have eight surfacing crews operating on the two properties this year; seven are our own employees and one a contractor, ARB out of Northwood, Iowa. The surfacing crew foremen are Mike Cherne at Chillicothe, Jason Teynor at Marquette, Remington Hill at Mason City, Kent Maxon at Waseca, Earl Ruchdaschel at Huron, Jared Hook at Philip and Bob Tech at Belle Fourche.

¨       As of the 3rd of June 2004, over 65,000 tons (over 860 car loads) of ballast has been delivered.  This is over 33% of the 200,000 tons expected to be delivered this year.

¨       The Transportation Department continues to do an excellent job moving the loads and empties to the needed locations and have dedicated power and a 60 car train to run from Brookings to Owatonna for the next few weeks to allow the ballasting operation to get further ahead of our surfacing crews.