Surfacing
Weekly Update #29
4
November 2004
ELEVEN SURFACING CREWS CONTINUE TO HAVE EXCELLENT
PRODUCTION!!
As of November 4 we have surfaced over 760
of the 800 pass miles that we had projected to be surfaced in the 2004
production year, over 95% of the total miles scheduled. All information from the field still
indicates to us that the schedule will be met or exceeded yet this fall.
There are currently 6
surfacing crews on the DM&E this year.
They are Kent Maxon’s east crew, Earl Ruckdashal’s central crew, Jared
Hook’s west crew, and Bob Tech’s
¨ The Railworks surfacing crew
will complete their work on the west end of the Huron sub this week and will
then travel to Brookings to surface between Brookings and
¨ Safetrak has just recently
gotten started and is currently working west from
¨ The ARB surfacing crew
continues to perform well and has already this year completed work on the
¨ Kent Maxon’s crew is west of
Balaton. They will make a final pass on the
¨ Earl Ruckdashal and Jared
Hook both have surfacing crews working on the PRC
¨ Bob Tech’s surfacing crew is
working near
¨ Remington Hill’s crew is
finishing up surfacing on the Calmar Rail Project
¨ Jason Teynor’s crew is
working on the
¨ Mike Cherne’s crew continues
to work northward on the
¨ As of October 21, 2004
nearly 250,000 tons of ballast has been distributed on both properties. This is over 95% of the 255,000 tons of
ballast that we now believe we will require to complete
this year’s projects. The Engineering
Department as a whole appreciates the cooperation we have received from both
Quarries and the transportation department to get all of this ballast unloaded.