Surfacing
Weekly Update #31
18
November 2004
SURFACING CREWS NEARING COMPLETION OF MAJOR
PROJECTS!!!
As of November 18th
we have surfaced over the 800 pass miles that we had scheduled to be surfaced
this year. Some of the surfacing crews
will continue to surface as long as possible to further improve rough areas on
the properties.
There are now 5 surfacing
crews still working on the DM&E and 5 surfacing crews on the IC&E. Of these 10 crews 7 are MOW crews from the
two properties and the other 3 are contractors.
The contractors will complete their projects within the next week or two
and the MOW crews will continue to surface until mother-nature forces us to
quit for the year.
¨ The Railworks and Safetrak
surfacing crews completed their projects on the Huron sub over the weekend and
both have left the property
¨ The ARB surfacing crew has
finished the Tyler CWR and will do some surfacing in the
¨ Kent Maxon’s crew completed
the surfacing on the BN connection track at
¨ Both Earl Ruckdashal’s and
Jared Hook’s surfacing crews will continue to work on the PRC sub until freeze
up.
¨ Bob Tech’s surfacing crew is
working near Colony, WY assisting with the switch and track renewal at that
location.
¨ Remington Hill’s crew has
finished up surfacing on the Calmar Rail Project and will spot surface other
areas of the
¨ Jason Teynor’s crew will
work on the
¨ Mike Cherne’s crew continues
to work northward on the
¨ As of November 18, 2004 over
255,000 tons of ballast has been distributed on both properties. This is 100% of total amount that we
originally forecast to unload this year and the Engineering Department as a
whole appreciates the cooperation we have received from both the LG Everist and
New Ulm Quarries and the transportation department to get all of this ballast
delivered and unloaded.